Goose Creek Trail 7

Secondary Logo_Full Color

The project will complete the Phase 7 portion of the Goose Creek trail from Hutto Blvd at Baker and provide a connection from Baker to Cedar Bayou Lynchburg through the Center Port utility power line easement with future expansion to the New Mall.

BUDGET: $540,765.00

WHY is this project needed: This trail connection will provide connectivity from W. Cedar Bayou Lynchburg to Bayland Marina. 

HOW LONG will this project take: This project will take 4 to 6 months with construction starting in Spring 2022. 

WHAT are the project improvements: The trail will be expanded into a 10-foot-wide concrete trail that includes a shared use path. This will finish the connection to the existing Country Club Cove Neighborhood sidewalk, which in turn, connects to McElroy Park.

Phase 7 Map

Goose Creek Trail Park Project Updates 


Goose Creek: The cross walk has been put down to finish off Phase 7 of the Goose Creek Trail.November 15, 2022 update

The cross walk has been put down to finish off Phase 7 of the Goose Creek Trail.


Goose Creek: The glow stone art is being tested and evaluated on the Goose Creek Trail.August 5, 2022 update

The glow stone art is being tested and evaluated on the Goose Creek Trail.


Goose Creek: The glow stone forms are going in!July 18, 2022 update

The glow stone forms are going in!


Goose Creek: Portions of the trail have been left open to prepare for unique art June 2, 2022 update

Portions of the trail have been left open at this time to prepare for unique art piece that will be installed. The pieces will be made from glow stones which will allow the artwork to glow in the dark.